Guide

Party wall notice periods and deadlines

The Act runs on a handful of fixed periods. Know them and you can plan a build to the week.

  • 1 or 2 months
  • 14 days
  • 10 days

The periods at a glance

WhatHow longRuns fromWhat it means
Notice before work to a party wallAt least 2 monthsService of the noticeEarliest start, unless the neighbour agrees to sooner
Notice before a boundary wall or excavationAt least 1 monthService of the noticeEarliest start, unless the neighbour agrees to sooner
Neighbour's reply14 daysThe day the notice is servedNo written consent means a dispute for section 2 and 6 notices
Counter-notice1 monthService of a party structure noticeThe neighbour can ask for extra work for their own benefit
Reply to a counter-notice14 daysService of the counter-noticeSilence means a dispute
Request to appoint a surveyor10 daysService of the requestAfter that, a surveyor can be appointed for them
Notice of entry onto next door's land14 daysService of the notice of entryShorter in an emergency
Appeal against an award14 daysService of the awardAppeal goes to the county court
Party structure notice lapses12 monthsService of the noticeIf the work has not begun

Periods of 14 days and 10 days count the day of service as day one. A notice sent by post is treated as served on the day it would normally arrive, so allow for that and keep proof of postage.

A worked example

A party structure notice for a loft conversion is served by hand on Monday 1 March 2027.

  1. Notice served. Day one of the 14 days.
  2. Last day for the neighbour to reply in writing.
  3. No reply, so a dispute is treated as having arisen. The 10-day request goes out the same day.
  4. Last day for the neighbour to appoint a surveyor.
  5. The building owner can appoint a surveyor on the neighbour's behalf.
  6. Last day for a counter-notice.
  7. Two months have run. Work can start from here, with the award in place.
  8. If work has not begun by now, the notice lapses.

Want the dates for your own notice? The notice checker works them all out from the date of service.

How to keep to time

  • Serve as soon as the design is settled, not when the builder is booked.
  • Get structural drawings early. Neighbours and their surveyors cannot agree an award without them.
  • Talk to your neighbours before the notice lands. A notice that arrives out of the blue is more likely to be met with dissent.
  • Consider one agreed surveyor for both sides. It is usually the quickest route.